NESO register tracker, edition 5: 21 to 28 September 2026
Seven days between files, and the TEC Register barely moved. Two projects joined, one left, net minus 10 MW. Read the full post
Both arrivals are batteries that are already built, Care Wolverhampton BEGA (49.9 MW at Penn GSP) and Care North Tawton BEGA (30 MW at Alverdiscott GSP). The single exit was Melksham Grid Park ESS & PV, 90 MW with a 2037 connection date.
Connection dates are the interesting part. Devol Moor Battery & Solar (400 MW) came forward 25 months to September 2027, and Bryn Tilti (106 MW) came forward 17 months to February 2027. Willington Energy Park (500 MW) went out seven months to October 2028. Taken together that’s +8.3 GW-months, the first week of this series in which dates moved earlier overall. Row and project methods agree, as all three are single-tranche.
On gates, seven projects picked up a Gate 1 label (708.9 MW) and Benthead Solar (63 MW) picked up Gate 2. One label went the other way: Equinor Celtic Sea 2 (1,000 MW) lost its Gate 1 label with nothing else on the row changing. That is currently unexplained.
A method change. From this edition the register level is the sum of every row on NESO’s file, 679.4 GW today. On that basis the levels shown in earlier editions were 3.4 to 4.4 GW low. The weekly movements do not change.
If a gate label can come off the register without a reason attached, how much weight can anyone put on the gate column when sizing the reformed queue?
Independent work, no client and no commercial interest in what the figures show. Whatever they show gets published.
Source: NESO Transmission Entry Capacity Register, files of 21 and 28 September 2026.