Departures, part 2: is any train in Europe leaving on time?
In part 1 the board was Euston’s, and London’s data centre train was showing DELAYED. If you want the one genuinely fast service out of London, though, you don’t go to Euston at all. You walk round the corner to St Pancras and catch the Eurostar. Read the full piece
That’s roughly where this edition ends up. The board is FLAP-D plus two: Frankfurt, London, Amsterdam, Paris and Dublin, the five markets the industry groups as FLAP-D, with Oslo added for the Nordics and Scotland added because Holyrood has put its own service on hold. Same board, same columns: the date that was scheduled or targeted, the date the latest public evidence says to expect, and a remark. The carriages show how full each market already is, using CBRE’s colocation vacancy for the first quarter of 2026. Where CBRE doesn’t publish a figure, the carriages are left blank.
Guy Massey’s US arrivals board started this series, and it’s still the best format I’ve found for a queue.
The board

London: DELAYED
I covered London in part 1, so briefly: NESO’s reformed pipeline holds more than 100 GW of large demand, most of it data centres, and around 13 GW of that can connect before 2030. A further 86 GW is slated for 2030 to 2035. Part 1: https://lnkd.in/p/egqJGnD8
The Caledonian Sleeper: HELD
The Caledonian Sleeper leaves from Euston too, and Scotland’s data centre service is currently held at the platform. This hold is in the planning system. On 16 September the Scottish Parliament rejected a Green motion for a moratorium, but agreed an amended motion, 80 votes to 26, which says no decisions on hyperscale applications should be made until national planning guidance is complete. The Scottish Government doesn’t accept that this is a moratorium. Its Minister for Public Finance has since told Holyrood’s Climate Action Committee that the guidance will be published before Christmas, and that the government doesn’t expect any applications to be decided before then.
Two directions now apply. Since August, planning authorities must notify Ministers of any data centre application above 50 MW, and since 17 September those applications have required a full environmental impact assessment. Around two dozen hyperscale applications are in the system. Scotland’s installed data centre capacity was estimated at 10 to 30 MW in 2024.
Frankfurt: DELAYED to the mid-2030s
Frankfurt’s distribution operator, NRM Netzdienste Rhein-Main, no longer works on first come, first served for large requests. Anything of 3.5 MW or more goes into a once-a-year pro-rata allocation, and at the West grid node the threshold drops to 1 MW until a new substation at Eschborn is commissioned. NRM’s own words are that demand clearly exceeds what the upstream transmission grid can supply, and it names the boom in data centre requests as one of the reasons. It expects the restrictions to last until the mid-2030s, when new TenneT supply points at Eschborn and Ostend come in. Mainova, NRM’s parent, says it and TenneT plan around 1,000 MW of additional supply capacity in the next few years, without a date.
One operator has had the answer in writing. Firstcolo was reportedly told that power for its planned Frankfurt expansion would not be available before 2035.
Frankfurt also adds conditions on top of the wait. New data centres coming into operation from July 2026 must meet a design PUE of 1.2 and source at least half their electricity from renewables under Germany’s Energy Efficiency Act, and the city restricts where data centres can be built through its own data centre concept. A bill to relax parts of that Act, giving new sites four years rather than two to meet the efficiency standard and moving the full renewables requirement from 2027 to 2030, has had its first reading in the Bundestag but has not yet passed.
Amsterdam: DELAYED from 2031 to 2036
In January, Liander published the results of TenneT’s recalibrated congestion study for Noord-Holland. For the Vijfhuizen part of the network, which serves Amsterdam Nieuw-West, Zuid and the Zuidas, the expected connection date moved from 2031 to 2036. Diemen moved from the end of 2036 to the end of 2037. Around 230 Amsterdam customers are waiting across those two areas.
It isn’t all one way. Oostzaan moved a year earlier, to 2029 to 2030, and Liander expects to grant around a fifth of the requests waiting there. In April a court in Arnhem upheld TenneT’s decision to put a 70 MW data centre request near Schiphol on the waiting list.
Planning is tight as well. Amsterdam’s stance is “no, unless”: new or expanded data centres over 2,000 m² or 5 MVA are not permitted under its zoning, and nationally, hyperscale sites of 10 hectares and 70 MW or more have been confined to two locations, Eemshaven and Middenmeer, since January 2024.
Amsterdam has the most spare space on the board at 9.4%, which can look odd for a market this constrained. It isn’t a contradiction. Vacancy measures halls already built and available to rent; the grid governs what gets built next.
Dublin: SUSPENDED
EirGrid’s May 2026 overview says it plainly: the greater Dublin region is considered fully constrained. Ireland has reopened applications under the regulator’s new large energy user policy, decided in December 2025, but reopening applications isn’t the same as reopening capacity. The new policy also changes what a data centre has to bring. Sites of 10 MVA or more must provide dispatchable generation or storage, on site or nearby, equal to their full import capacity, and match 80% of their annual demand with new Irish renewables over six years. The policy is now the subject of a judicial review.
The scheduled date on the board, 2028, is the date reported in 2022 for the end of EirGrid’s Dublin pause. There is no expected date to put against it.
Paris: the Eurostar, EXPRESS for fast-track sites only
Paris is the one service on the board running early, and it’s worth being precise about why. In May 2025 France’s regulator, CRE, approved a fast-track procedure under which the State identifies large sites, 400 MW to over 1 GW, whose connection to the 400 kV network isn’t limited by grid capacity, with a 2028 to 2029 target. RTE lists five such sites, two in Île-de-France and three in Hauts-de-France, and four had been allocated by Choose France in May 2026. The first fast-track contract, signed with RTE in January 2026 for the Campus IA site at Fouju, provides 240 MW by the end of 2027, ahead of the target, and 700 MW before the end of 2029.
Off the fast track, France looks much more like everyone else. RTE had reserved nearly 18 GW for around 80 data centre projects by May 2026, against about 5 GW at the end of 2024, with around 7 GW in Île-de-France. Operators report ordinary connection waits of two to seven years.
There’s also a detail in RTE’s figures that every grid planner will recognise. Recently connected data centres draw on average about 20% of the power they asked for, and RTE expects it to take 10 to 15 years for them to reach around 80%.
So the express runs because the State chose the route and the stations before the passengers arrived.
Oslo: a cheaper ticket, but the platform is filling
I started this edition expecting the Nordics to be the train running on time. The evidence doesn’t support that. Statnett’s own median times from project start to operation are four to six years for a transformer upgrade, five to ten for a new substation and seven to twelve for a new line. Mature applications for consumption rose by around 2,000 MW year on year in the first half of 2026, and Statnett describes the queue as growing sharply, while 600 MW of new consumption was connected over twelve months. Stricter maturity rules for new applications came in from July.
Elsewhere in the region, Denmark’s Energinet paused new connection agreements in March with around 60 GW of consumption queued against peak demand of around 7 GW, and Finland is drafting rules to replace first come, first served. The Nordic offer is cleaner and cheaper power. It isn’t a faster connection.
What the board says about the UK
My reading: every market on this board that queues by order of arrival shows DELAYED or worse. The one service that runs early is the one where the State picked the sites first and built the line to them.
The UK has the pieces of that. AI Growth Zones designate sites, and Gate 2 reorders the queue by readiness and need. Whether they add up to a Eurostar, or just a revised timetable for the same trains, is the question for the next twelve months. While the answer comes, each month a data centre waits costs its investors between £65,000 and £105,000 per MW of IT load, the floor I set out in part 3 of “Who pays for the wires?”. Part 3: https://lnkd.in/p/eFCyB6vb
Should the UK pick its fast-track sites the way France has, or keep letting the queue decide?
Sources
NESO results of connections reform, via DCD, 9 December 2025
NRM Netzdienste Rhein-Main, Pro-Rata-Verfahren Strom (2026/27 allocation round)
Mainova, Stromnetz (grid investment and 1,000 MW plan with TenneT)
Energieeffizienzgesetz (EnEfG), section 11
Deutscher Bundestag, first reading of the Energy Efficiency Directive implementation bill (21/8027), 24 September 2026
Stadtplanungsamt Frankfurt, Rechenzentrenkonzept (2022)
Liander, Langere wachttijden in Noord-Holland maar ook eerder ruimte voor deel Amsterdamse klanten, 15 January 2026
Gemeente Amsterdam, Vestigingsbeleid datacenters 2020–2030, eerste herziening (2026)
Tweede Kamer, Kamerstuk 26643-819 (hyperscale data centre locations)
EirGrid, Data Centre Constrained Area Overview, May 2026
CRU, Large Energy Users Connection Policy decision CRU2025236, 12 December 2025
ClientEarth, press release on judicial review, 27 April 2026
CRE, fast-track procedure for large consumers, 7 May 2025
RTE, Les data centers en chiffres clés (updated 1 June 2026)
RTE, accelerated connection contract with Campus IA (Fouju), press release, 26 January 2026
Statnett, How to get capacity for direct customers
Statnett, half-year report 2026
Energinet, temporary pause in new grid connections, 2 March 2026
CBRE, Global Data Center Trends 2026 and European Data Centres Figures Q1 2026
Mark D. Moore, “Who pays for the wires?” Part 3, LinkedIn, 9 October 2026
Mark D. Moore, “Departures: where the UK’s data centre trains actually stand”, LinkedIn, 30 October 2026
Scottish Parliament, motion S7M-01177 as amended, 16 September 2026
Scottish Government, Chief Planner letter and EIA Direction, 16 September 2026; Notification Direction, 17 August 2026
Minister for Public Finance to the Climate Action Committee, 8 October 2026
Reported, not primary: Firstcolo (dpa via Energie & Management, 18 March 2026); Arnhem court ruling (NL Times, 29 April 2026); Paris ordinary waits (operator statements, 2026); Finland (Borenius, 26 August 2026); Dublin 2028 (DCD, 11 January 2022); Scotland autumn 2026 decision timing (DCD, 16 September 2026); two dozen Scottish applications (CIBSE Journal, 1 October 2026); Scotland 10 to 30 MW installed (DSIT and Scottish Enterprise, via APRS, December 2025).
Provenance: Synthesis, with original comparison across markets.
Earlier posts and articles are archived at markdmoore.co.uk








