Mark Moore


Glossary

The terms I use in my published work, what I mean by them, and where each one comes up. It grows as new terms appear in the work. Where a term has a primary source, it is linked.

GW-months Net movement Row-level and project-level date movement Derived residual Counting basis Snapshot provenance Carried forward Returning rows (date reversion) TEC Register Embedded Register (NESO) Embedded Capacity Register (ECR) Interconnector Register Project Number (PRO-nnnnnn) Tranche Gate 1 and Gate 2 Countersignature Accepted to connect Unique Site Identifier Maximum Import Capacity (MIC) Rated IT load TMO4+ Clean Power 2030 User Commitment (CMP192) Wider Cancellation Charge Queue management milestones (CMP376) Progression Commitment Fee (CMP448) CMP470 Curate Data Centre Service and Enterprise Basis ASTI Non-firm connection CMP446 Curtailed or non-firm export offer Gate 2 to Whole Queue (G2TWQ) Strategic Spatial Energy Plan (SSEP) Data Centre Commitment Fee Transmission Entry Assessment TNUoS Transmission demand residual DUoS BSUoS RIIO-3 and RIIO-ED2 Regulatory Asset Value (RAV) Renewables Obligation (RO) Feed-in Tariffs (FiT) Capacity Market levy and Periods of High Demand BICS Private wire Second job NSIP and section 35 direction Power usage effectiveness (PUE) FLAP-D AI Growth Zones Data Centre Covenant Final investment decision (FID) Bridge (bridging power) Section 36 consent Colocation vacancy CUSC DCUSA National Terms of Connection NESO DNO Transmission owners (NGET, SPT, SHET) Ofgem GB Grid

My measures and method

GW-months

The measure I use for connection-date movement in the TEC tracker: the capacity of each agreement whose date moved, multiplied by the number of months it moved, added up across the register. Moves to a later date count as negative, moves to an earlier date as positive. A running total is carried from edition to edition.

Used in: TEC tracker, Edition 2 · TEC tracker, Edition 4 · TEC tracker, Edition 5 · TEC tracker, Edition 6 · TEC tracker, Edition 7 · TEC tracker, Edition 8 · TEC tracker, Edition 9 · TEC tracker, Edition 10

Net movement

The change in total contracted capacity on a register between two files, after joiners and leavers. Where capacity has moved from one NESO register to another, I record it as a transfer rather than as capacity leaving the queue.

Used in: TEC tracker, Edition 2 · TEC tracker, Edition 3 · TEC tracker, Edition 4 · TEC tracker, Edition 5 · TEC tracker, Edition 6

Row-level and project-level date movement

Two ways of counting date movement. Row-level compares the date on each register row between files. Project-level groups a project’s rows together, so it also catches capacity moved between tranches when no row’s date changes. From Edition 5 the tracker reports both.

Used in: TEC tracker, Edition 4 · TEC tracker, Edition 5 · TEC tracker, Edition 6 · TEC tracker, Edition 7 · TEC tracker, Edition 8 · TEC tracker, Edition 9 · TEC tracker, Edition 10

Derived residual

A figure obtained by subtracting one register column’s movement from another’s. It is arithmetic, not a measurement: the register does not record what happened to the capacity it represents, so I never describe it as a withdrawal.

Used in: Four gigawatts left a connection register

Counting basis

The stated rule for how a total was added up: which column, which files, whether rows were deduplicated. I give it wherever a total appears, because the registers allow more than one defensible answer.

Used in: ECR tracker, Edition 1 · Four gigawatts left a connection register · TEC tracker, Edition 7

Snapshot provenance

NESO overwrites each register file when it publishes the next, so a file not downloaded on the day is gone. The publication date in the filename is the only record of which snapshot a figure comes from, which is why downloaded files are never renamed.

Used in: Four gigawatts left a connection register

Published basis and control

The two totals I run over every TEC Register file. The published basis is the sum of every row, MW connected plus MW increase or decrease, and is the level I report. The control is built from the register’s own project totals. The two are expected to agree within 0.1 GW.

Used in: TEC tracker, Edition 7 · TEC tracker, Edition 8 · TEC tracker, Edition 10

Basis divergence

The gap between the published basis and the control. When it exceeds the 0.1 GW tolerance, the gap is reported as a finding and its cause is explained. On the 13 October 2026 file it was 1.368 GW, caused by a change in how NESO recorded two staged projects, not by any change in capacity.

Used in: TEC tracker, Edition 7

Inclusion test

The four conditions a scheme must meet to appear on my UK data centre power map, each resting on a developer, planning authority or government source: a named scheme at a specific location; an MW figure stated by the developer, planning authority or government; a publicly stated supply arrangement; and a dated status. A figure that appears only in trade press does not qualify.

Used in: Fourteen UK data centres, one test · Fourteen UK data centre schemes passed the test · UK data centre map, Edition 2: live Tuesday 10 November · UK data centre map, Edition 2: live today

Green, Amber and Red rating

The rating on my UK data centre power map. Green: new clean supply contracted to the site, or co-located with it, with the counterparty or asset named, and no on-site fossil prime power. Amber: grid supply only, or a clean-power claim not tied to a named new asset. Red: on-site or dedicated gas or other fossil generation planned as the primary or bridging supply. Standby plant is recorded but does not change the rating.

Used in: Fourteen UK data centres, one test · Fourteen UK data centre schemes passed the test · UK data centre map, Edition 2: live Tuesday 10 November · UK data centre map, Edition 2: live today

Hours of leakage

A scale comparison I use for water figures: the volume divided by the leakage rate for England and Wales, giving the number of hours the public supply network takes to lose that volume through leaks. The basis is Ofwat’s 2024-25 figure of 2,869 million litres a day. On that basis 1.88bn litres is about 16 hours. It puts a number in context; it does not mean the two volumes are interchangeable at any one site.

Used in: A year of data centre water, measured in hours of leakage

Carried forward

A register that has not been refreshed since the last edition, carried unchanged into the ECR tracker’s totals. In Edition 2, NGED’s file was still its August edition and SP ENW’s download was identical to September’s, so both were carried forward. Between them they held 40.2 GW, about 36% of the national total, and all of the month’s movement came from the four operators that did refresh.

Used in: ECR tracker, Edition 2

Returning rows (date reversion)

A TEC Register row whose connection month has changed to a month the same row had already held on an earlier file. In Edition 9, thirteen of the fourteen rows that changed connection month were returning rows. Dates moved out by a net 66.2 GW-months, and the returning rows accounted for minus 92.3 of that.

Used in: TEC tracker, Edition 9

Candidate (map)

A watch-list scheme on my UK data centre map that is one or two checks away from the map.

Used in: UK data centre map, Edition 2: live Tuesday 10 November · UK data centre map, Edition 2: live today

Registers and the data in them

TEC Register

NESO’s published list of projects holding transmission connection agreements, giving each project’s capacity (Transmission Entry Capacity, in MW), connection site, connection date and Gate status.

Source: NESO, TEC Register
Used in: TEC tracker, Edition 2 · TEC tracker, Edition 3 · TEC tracker, Edition 4 · The seven projects the NAO singled out · TEC tracker, Edition 1 · Grid connection dates are sliding · The TEC Register doesn’t show connections reform yet · Seven projects, 4.2 GW, gone from the register · Connection dates and grid upgrades · TEC tracker, Edition 5 · Why does CMP470 make sense? · Why does CMP470 make sense? (post) · Fixing the rules before the result · GB Grid can’t buy its way up the queue · TEC tracker, Edition 6 · Fourteen UK data centres, one test · Fourteen UK data centre schemes passed the test · TEC tracker, Edition 7 · TEC tracker, Edition 8 · TEC tracker, Edition 9 · Response to Ofgem on Transforming Connections Data · TEC tracker, Edition 10 · TEC tracker, Edition 11

Embedded Register (NESO)

NESO’s register of embedded, distribution-connected projects in Scotland that have a bearing on the transmission system. It covers Scotland only and is not additive to the DNO Embedded Capacity Registers.

Source: NESO, Embedded Register
Used in: TEC tracker, Edition 4 · Four gigawatts left a connection register

Embedded Capacity Register (ECR)

The register each distribution network operator publishes of generation and storage schemes connected, or accepted to connect, to its network, in a common template set under DCUSA. The six DNO groups each publish their own, in their own format.

Source: DCUSA
Used in: ECR tracker, Edition 1 · Four gigawatts left a connection register · Are smaller data centres actually faster to power? · ECR tracker, Edition 2

Interconnector Register

NESO’s register of interconnector connection agreements. An interconnector leaving the TEC Register may have moved here, so the tracker checks this register before counting one as gone.

Source: NESO, Interconnector Register
Used in: TEC tracker, Edition 4 · TEC tracker, Edition 10

Project Number (PRO-nnnnnn)

The identifier on the TEC Register that the tracker uses as its row key, compared from file to file. Where a project is split into tranches, each tranche sits on its own row under the same project.

Source: NESO, TEC Register
Used in: TEC tracker, Edition 4 · TEC tracker, Edition 7

Tranche

A portion of a project’s capacity carried on its own register row, with its own connection date.

Used in: TEC tracker, Edition 4 · TEC tracker, Edition 5 · TEC tracker, Edition 6 · TEC tracker, Edition 10

Gate 1 and Gate 2

The two stages of the reformed connections process. A project at Gate 2 has met the readiness and strategic alignment tests and holds a confirmed queue position; a project at Gate 1 has not yet. The tracker counts agreements that gain a Gate label in each week’s file.

Source: NESO, Connections Reform
Used in: TEC tracker, Edition 2 · TEC tracker, Edition 3 · TEC tracker, Edition 4 · Five controls on the connections queue · TEC tracker, Edition 1 · The TEC Register doesn’t show connections reform yet · TEC tracker, Edition 5 · Why does CMP470 make sense? · Why does CMP470 make sense? (post) · TEC tracker, Edition 6 · The WEF’s new data centre playbook · Five conferences on energy · TEC tracker, Edition 7 · The latest grid queue slip came from the engineering desk · TEC tracker, Edition 8 · TEC tracker, Edition 9 · Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post) · TEC tracker, Edition 10 · Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post) · Departures, part 2: is any train in Europe leaving on time? · TEC tracker, Edition 11

Countersignature

The customer’s signature on a connection offer, which completes the agreement. “A Gate recorded on countersignature” in the tracker means a Gate label appearing on an agreement in that week’s file.

Used in: TEC tracker, Edition 3 · TEC tracker, Edition 4 · TEC tracker, Edition 1 · The TEC Register doesn’t show connections reform yet

Accepted to connect

The ECR status of a scheme that has accepted a connection offer but is not yet energised. The ECR tracker sums Accepted to Connect Registered Capacity as each operator publishes it.

Used in: ECR tracker, Edition 1 · Four gigawatts left a connection register · ECR tracker, Edition 2

Unique Site Identifier

The ECR field that the governing template defines as an identifier that “distinguishes each entry uniquely rather than use site name”. Mandated since February 2026; not yet published consistently by all six DNO groups.

Source: DCUSA
Used in: Four gigawatts left a connection register

Maximum Import Capacity (MIC)

The import capacity agreed in a site’s connection agreement, and the measure against which some regimes set their thresholds and under which the National Terms of Connection allow unused capacity to be reviewed.

Source: ENA, National Terms of Connection
Used in: 72.8 GW requested, 4 GW connecting, 1.4 GW drawn · Six rulebooks set a data centre size line · 73 GW queueing, and no count of the capacity sitting idle

Rated IT load

The power rating of a data centre’s IT equipment, excluding cooling and other site load. It sits below the site’s connection capacity, which is why a scheme can fall on different sides of thresholds set on each.

Used in: Six rulebooks set a data centre size line · Ofgem’s data centre milestones may bite at 1MW · If the UK had its own Elon Musk, how fast could they build a data centre? · Fourteen UK data centres, one test · Who holds the cards when the biggest AI buyers go small · If the UK had its own Elon Musk, what would the time be worth? · If the UK had its own Elon Musk, what would the time be worth? (post) · Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post) · Three lines to power, and the main one is suspended

Connections reform and queue controls

TMO4+

The reformed, gated connections process for GB, which sorts projects into Gate 1 and Gate 2 and tests readiness and fit against Clean Power 2030 at entry.

Source: NESO, Connections Reform
Used in: Five controls on the connections queue · Is curtailment quietly controlling the small end of the queue?

Clean Power 2030

The government’s action plan for a clean power system by 2030, published December 2024. It sets the capacity ranges that connections reform tests projects against.

Source: DESNZ, Clean Power 2030 Action Plan
Used in: Five controls on the connections queue · The seven projects the NAO singled out · GB Grid can’t buy its way up the queue · Flexible connections and the AIEC

User Commitment (CMP192)

The CUSC arrangement under which a project carries part of the cost of the network built for it, through liability that grows towards energisation.

Source: NESO, CMP192
Used in: Five controls on the connections queue · Why does CMP470 make sense? · Is curtailment quietly controlling the small end of the queue?

Wider Cancellation Charge

The charge a project faces under User Commitment if it terminates, reflecting the wider network works built on its behalf.

Source: NESO, CMP192
Used in: Five controls on the connections queue

Queue management milestones (CMP376)

Progress milestones written into the CUSC in 2023. Projects that miss them can be removed from the queue.

Source: NESO, CMP376
Used in: Five controls on the connections queue · Ofgem’s data centre milestones may bite at 1MW · Is curtailment quietly controlling the small end of the queue?

Progression Commitment Fee (CMP448)

A fee on projects between Gate 2 and Milestone 1, approved December 2025. It stays dormant unless terminations pass a set threshold.

Source: NESO, CMP448
Used in: Five controls on the connections queue · Is curtailment quietly controlling the small end of the queue?

CMP470

A proposed CUSC modification introducing an Oversubscribed Technologies Commitment Fee. It applies when a technology’s capacity in the queue exceeds its government target by more than 50%. Ofgem published a minded-to consultation on 17 September 2026.

Source: Ofgem, CMP470 consultation
Used in: Five controls on the connections queue · Why does CMP470 make sense? · Why does CMP470 make sense? (post) · The WEF’s new data centre playbook · Response to Ofgem on CMP470 · What is the grid worth to a data centre? · Is curtailment quietly controlling the small end of the queue?

Curate

Ofgem’s 2026 consultation on data centre connection reforms, published 29 July 2026, covering commitment fees and queue management milestones for data centres.

Source: Ofgem, Proposed data centre connection reforms
Used in: Ofgem’s data centre milestones may bite at 1MW · Six rulebooks set a data centre size line · Curate consultation response · Flexible Hybrid Grid Connection · Why does CMP470 make sense? · The WEF’s new data centre playbook · Who holds the cards when the biggest AI buyers go small · Who holds the cards (post) · What is the grid worth to a data centre? · The Data Centre Covenant: what the Budget offered data centres · Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post) · 73 GW queueing, and no count of the capacity sitting idle · Friday’s board said Oslo’s platform was filling

Data Centre Service and Enterprise Basis

Definitions in the draft CUSC text consulted on under Curate. A Data Centre Service is a facility at 1 MW or above, or 10 MW where it is on an Enterprise Basis, meaning it serves only its owner’s own undertaking.

Source: Ofgem, Proposed data centre connection reforms
Used in: Ofgem’s data centre milestones may bite at 1MW · Six rulebooks set a data centre size line · Curate consultation response

ASTI

Accelerated Strategic Transmission Investment: Ofgem’s 2022 framework for fast-tracking large onshore transmission projects needed for 2030.

Source: Ofgem, ASTI decision
Used in: The seven projects the NAO singled out · Connection dates and grid upgrades · GB Grid can’t buy its way up the queue · Mind the gap: the kit turns up, the grid doesn’t

Non-firm connection

A connection on terms that are not firm, explored as a way to let demand in the queue connect sooner. The AI Energy Council’s April 2026 meeting looked at non-firm connections alongside curtailment during stress events and voluntary flexibility, and Ofgem’s June 2026 update on demand connections reform describes non-firm and phased connections with a path to firm. For a data centre, a bridge strategy becomes significantly easier if a proportion of the requirement is supplied through a non-firm connection.

Source: Ofgem, Connect update: demand connections reform, June 2026 (PDF)
Used in: Flexible connections and the AIEC · Is curtailment quietly controlling the small end of the queue? · Loughton without the farmland, or the wait · Three lines to power, and the main one is suspended

CMP446

A CUSC modification that raised the transmission assessment threshold in England and Wales from 1 MW to 5 MW in May 2025, which should have made the small end of the queue easier.

Source: NESO, CMP446
Used in: Is curtailment quietly controlling the small end of the queue?

Curtailed or non-firm export offer

A distribution connection offer that comes back with export curtailed, or without firm export. For on-site C&I solar the export route is the funder’s backstop if the customer defaults, so a curtailed offer weakens it and the project can stall before FID. It never shows up as a refused connection, has no CMP number and is not counted, which is why I describe it as a possible sixth control on the queue.

Used in: Is curtailment quietly controlling the small end of the queue?

Gate 2 to Whole Queue (G2TWQ)

The process that issues Gate 2 offers, the reformed connection offers that decide where each project sits in the queue. Phase 1 offers, already extended once to 30 September 2026, can now be issued by 31 October, after Ofgem agreed a second extension on 2 October. Phase 2 offers remain due by 31 January 2027, and each holder then has 90 days to accept.

Source: Ofgem, agreement on alternative G2TWQ timetable
Used in: Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post) · Three lines to power, and the main one is suspended

Strategic Spatial Energy Plan (SSEP)

The plan for where energy infrastructure will be built, commissioned in October 2024, when the government said the first iteration would be published in 2026. NESO now expects to deliver the final plan in Autumn 2027, and on 23 October 2026 the government moved its statutory deadline to 31 December 2027. The Centralised Strategic Network Plan and the Regional Energy Strategic Plans follow by the end of 2028.

Source: DESNZ, Strategic Spatial Energy Plan: deadline extension
Used in: Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post)

Data Centre Commitment Fee

Proposed under Curate: £237,500 to £712,500 per MW, held from acceptance until energisation. The government expects it to apply to projects above 40 MW that connect to or affect the transmission system.

Source: Ofgem, Proposed data centre connection reforms
Used in: Three lines to power, and the main one is suspended

Transmission Entry Assessment

The ENA’s working name for any case where NESO is asked to assess a distribution project’s effect on the transmission network. There is no national threshold for demand; each DNO decides case by case.

Used in: Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post)

Licence backstop

The regulatory target date for an ASTI reinforcement. About 62% of the capacity on dated TEC Register entries at ASTI-linked substations sits beyond it, a median of two years after the target date: an association with a regulatory date, not an engineering programme.

Used in: Mind the gap: the kit turns up, the grid doesn’t

Self-build

Letting a customer build every sole-use asset between its site and the existing transmission system, well beyond today’s 2 km limit.

Used in: Self-build fixes the last two kilometres. Who fixes the rest?

Enabling and wider works

The works that set the connection date, so that building sole-use assets quicker does not mean an earlier connection. Reinforcing the existing network stays with the incumbent transmission owners.

Used in: Self-build fixes the last two kilometres. Who fixes the rest?

Second test

How a load behaves once it is connected, as distinct from who gets a place in the queue.

Used in: Friday’s board said Oslo’s platform was filling

Charging and price control

TNUoS

Transmission Network Use of System charges: what users pay for the transmission network, set annually by NESO.

Source: NESO, Final TNUoS Tariffs 2026/27 (PDF)
Used in: What a data centre actually buys from the grid · What sits inside the data centre price gap

Transmission demand residual

The fixed part of transmission charges for demand sites, charged per site per day by band rather than by the power drawn. In the top band for 2026/27 it is £20,829.24 a day.

Source: NESO, Transmission Demand Residual guidance (PDF) · NESO, Final TNUoS Tariffs 2026/27 (PDF)
Used in: What a data centre actually buys from the grid · The haulage deal nobody would sign · What sits inside the data centre price gap · Ofgem built a network charge that is very hard to avoid · 73 GW queueing, and no count of the capacity sitting idle

DUoS

Distribution Use of System charges: what customers pay for the local distribution network. Since April 2023 they also carry the reinforcement costs no longer charged to connecting demand.

Source: Ofgem, Access and Forward-Looking Charges SCR decision
Used in: What a data centre actually buys from the grid

BSUoS

Balancing Services Use of System charges: the cost of keeping supply and demand matched in real time, charged to final demand only since April 2023.

Used in: What a data centre actually buys from the grid · What sits inside the data centre price gap

RIIO-3 and RIIO-ED2

Ofgem’s price controls for the network companies. RIIO-3 covers transmission from 1 April 2026; RIIO-ED2 covers distribution. Each sets allowed revenue, including an allowed return on equity, for a five-year period.

Source: Ofgem, RIIO-3 Final Determinations · Ofgem, RIIO-ED2 Final Determinations
Used in: What a data centre actually buys from the grid · The haulage deal nobody would sign

Regulatory Asset Value (RAV)

The regulated value of a network company’s asset base. Spending added to it (“slow money”) earns a return and is recovered over the assets’ lives; spending recovered in the same year is “fast money”.

Source: Ofgem, RIIO-ED2 Final Determinations
Used in: What a data centre actually buys from the grid · The haulage deal nobody would sign

Private wire

A direct line from nearby generation to a site, bypassing the network for the power it carries. It avoids usage-based charges on that power but not the fixed residual charges, if the site stays grid-connected.

Source: Ofgem, Targeted Charging Review decision
Used in: What a data centre actually buys from the grid · The haulage deal nobody would sign · What sits inside the data centre price gap · Fourteen UK data centres, one test · Fourteen UK data centre schemes passed the test · UK data centre map, Edition 2: live today

Renewables Obligation (RO)

A levy on every MWh a supplier sells. For 2026/27 the obligation is 0.472 certificates per MWh at the £69.34 buy-out price, which comes to £32.73 per MWh.

Source: DESNZ, Renewables Obligation level calculations 2026 to 2027
Used in: Not all data centres are the same, Part 1: what they pay · Not all data centres are the same, Part 1: what they pay (post)

Feed-in Tariffs (FiT)

A levy recovering the costs of the Feed-in Tariff scheme: about £7.16 per MWh on the last scheme year Ofgem has reported.

Source: Ofgem, Feed-in Tariffs Annual Report, Scheme Year 15
Used in: Not all data centres are the same, Part 1: what they pay · Not all data centres are the same, Part 1: what they pay (post)

Capacity Market levy and Periods of High Demand

The Capacity Market cost is charged only on electricity drawn between 16:00 and 19:00 on working days from November to February: 246 hours this winter.

Used in: Not all data centres are the same, Part 1: what they pay · Not all data centres are the same, Part 1: what they pay (post)

BICS

The British Industrial Competitiveness Scheme. It removes RO and FiT costs for eligible manufacturers from April 2027 and the Capacity Market cost from October 2027. Data centres are not eligible.

Source: GOV.UK, BICS guidance for applicants
Used in: Not all data centres are the same, Part 1: what they pay · Not all data centres are the same, Part 1: what they pay (post)

Data centres and on-site power

Time to power

The time from the decision to build to first power on site. I use it to compare routes to power for a new data centre, against the 122 days xAI took in Memphis.

Used in: If the UK had its own Elon Musk, how fast could they build a data centre? · If the UK had its own Elon Musk (post) · If the UK had its own Elon Musk, what would the time be worth? · If the UK had its own Elon Musk, what would the time be worth? (post)

Bring your own power

Building generation on site to power a data centre rather than waiting for a grid connection. In England the size of the plant decides which permitting and planning rules apply.

Used in: If the UK had its own Elon Musk, how fast could they build a data centre? · If the UK had its own Elon Musk, what would the time be worth? · Departures: where the UK’s data centre trains actually stand · Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post)

Virtual pipeline

Compressed gas delivered to a site by trailer, carrying the load until a permanent gas connection arrives.

Used in: If the UK had its own Elon Musk, how fast could they build a data centre?

Second job

My reading of which private generating plant lasted as public supply took over: the plant that lasted tended to have a second job. ICI’s Wilton station on Teesside has supplied electricity and process steam to the chemical complex since March 1952. At Slough, the energy-from-waste plant that replaced the old units exports power to the grid and supplies steam to a factory next door. For on-site power at a data centre, the question is what the plant will be doing the day the grid connection is energised.

Used in: Who pays for the wires? The factories got there first

NSIP and section 35 direction

A nationally significant infrastructure project needs a development consent order rather than ordinary planning permission. A generating station above 50 MW of electrical output onshore in England is one. Since 8 January 2026, data centres can opt into the regime through a section 35 direction under the Planning Act 2008. On the Planning Inspectorate’s 2026 averages, a decision takes about 16 months from submission, with pre-application on top.

Source: Planning Act 2008, sections 14 and 15 · Forsters, data centres brought into the NSIP regime
Used in: If the UK had its own Elon Musk, how fast could they build a data centre? · Fourteen UK data centres, one test · Departures: where the UK’s data centre trains actually stand · Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post)

Power usage effectiveness (PUE)

The ratio of a data centre’s power at the meter to the power used by its IT equipment, once cooling and redundancy are counted. Google reports a 2025 fleet average of 1.09, and the Uptime Institute’s 2025 survey puts the global average at 1.54; on those bounds, 30 MW of IT means about 33 MW to 46 MW at the meter. The Data Centre Covenant asks for a design PUE of 1.3 or better.

Source: HM Treasury, The Data Centre Covenant
Used in: Who holds the cards when the biggest AI buyers go small · Departures: where the UK’s data centre trains actually stand · The Data Centre Covenant: what the Budget offered data centres · Departures, part 2: is any train in Europe leaving on time?

FLAP-D

Europe’s main data centre markets: Frankfurt, London, Amsterdam, Paris and Dublin.

Used in: Departures: where the UK’s data centre trains actually stand · Departures, part 2: is any train in Europe leaving on time? · Departures, part 2: is any train in Europe leaving on time? (post)

AI Growth Zones

Sites designated by the government for AI infrastructure, first announced in January 2025 with Culham designated first. There are now at least five. Each has to show it can support at least 500 MW of AI infrastructure. The government’s own Delivering AI Growth Zones paper calls timely grid connection the single biggest blocker.

Source: DSIT, AI Growth Zones
Used in: Andy Burnham can make the UK the fastest time to power · Andy Burnham can make the UK the fastest time to power (post) · Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post) · Three lines to power, and the main one is suspended · Departures, part 2: is any train in Europe leaving on time?

Data Centre Covenant

Announced in the Budget on 28 October 2026. It offers “strategic” projects priority connections, the transfer of pre-2030 connection contracts and temporary on-site power while they wait, in return for a local benefit plan, a design PUE of 1.3 or better and annual energy and water reporting. There is no MW threshold, no criteria and no application route yet.

Source: HM Treasury, The Data Centre Covenant
Used in: Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post) · The Data Centre Covenant: what the Budget offered data centres

Final investment decision (FID)

The point at which a project’s backers commit to build it. A curtailed export offer can stop a small solar deal reaching FID without ever showing up as a refused connection. Last winter 71 data centre projects, around 20 GW, told NESO they had reached FID, self-reported.

Used in: Is curtailment quietly controlling the small end of the queue? · What does the wait add up to? (article)

Bridge (bridging power)

A smaller on-site supply, from gas engines, batteries or both, that runs part of a site until its grid connection arrives.

Used in: Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post) · UK data centre map, Edition 2: live today

Section 36 consent

Consent from Scottish Ministers, under section 36 of the Electricity Act 1989, for a generating station over 50 MW in Scotland.

Used in: Three lines to power, and the main one is suspended

Colocation vacancy

The share of data centre halls already built and available to rent. It measures what is built, not what the grid lets come next.

Source: CBRE, European Data Centres Figures Q1 2026
Used in: Departures, part 2: is any train in Europe leaving on time? · Departures, part 2: is any train in Europe leaving on time? (post)

Codes and bodies

CUSC

The Connection and Use of System Code: the industry code governing connection to, and use of, the GB transmission system. Changes to it are made through numbered modifications (CMPnnn).

Source: NESO, CUSC
Used in: Five controls on the connections queue · Ofgem’s data centre milestones may bite at 1MW

DCUSA

The Distribution Connection and Use of System Agreement, the equivalent multi-party agreement for the distribution networks. It governs the Embedded Capacity Register template.

Source: DCUSA
Used in: Four gigawatts left a connection register

National Terms of Connection

The standard terms, published through the Energy Networks Association, on which distribution-connected customers are connected. Section 3 includes the clause allowing a network operator to propose reducing unused import capacity.

Source: ENA, National Terms of Connection
Used in: 72.8 GW requested, 4 GW connecting, 1.4 GW drawn · Great Britain’s data centre queue, in three numbers

NESO

The National Energy System Operator, which runs the GB transmission system, administers the CUSC and publishes the TEC, Embedded and Interconnector Registers.

Used in: TEC tracker, Edition 2 · TEC tracker, Edition 3 · TEC tracker, Edition 4 · 72.8 GW requested, 4 GW connecting, 1.4 GW drawn · TEC tracker, Edition 5 · Why does CMP470 make sense? · TEC tracker, Edition 6 · The WEF’s new data centre playbook · Fourteen UK data centres, one test · TEC tracker, Edition 7 · TEC tracker, Edition 9 · Flexible connections and the AIEC · Data centres, measured in Jackdaws · Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post) · Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post) · Departures, part 2: is any train in Europe leaving on time?

DNO

Distribution network operator. Six DNO groups run Great Britain’s fourteen distribution licence areas and each publishes its own Embedded Capacity Register.

Used in: ECR tracker, Edition 1 · Four gigawatts left a connection register · ECR tracker, Edition 2 · Is curtailment quietly controlling the small end of the queue? · Three lines to power, and the main one is suspended

Transmission owners (NGET, SPT, SHET)

The companies that own the transmission network in their areas: National Grid Electricity Transmission in England and Wales, SP Transmission in southern Scotland, and Scottish Hydro Electric Transmission in northern Scotland.

Used in: TEC tracker, Edition 3

Ofgem

The energy regulator for Great Britain. It approves code modifications and sets the network price controls.

Used in: Five controls on the connections queue · Ofgem’s data centre milestones may bite at 1MW · What a data centre actually buys from the grid · Why does CMP470 make sense? · Why does CMP470 make sense? (post) · Flexible connections and the AIEC · Departures: where the UK’s data centre trains actually stand · Response to Ofgem on Transforming the Connections Experience · Response to Ofgem on Transforming Connections Data · Three lines to power, and the main one is suspended · Three lines to power, and the main one is suspended (post) · Not all data centres are the same, Part 1: what they pay

GB Grid

A publicly owned company inside Great British Energy, announced in September 2026, that will invest in networks and can co-invest in connections that businesses build themselves. The government calls it Great British Grid. Its operating rules and timetable have not yet been published.

Source: DESNZ, Great British Grid to speed up connections and cut bills
Used in: GB Grid can’t buy its way up the queue · Andy Burnham can make the UK the fastest time to power · Andy Burnham can make the UK the fastest time to power (post) · Departures: where the UK’s data centre trains actually stand · Departures: where the UK’s data centre trains actually stand (post) · Self-build fixes the last two kilometres. Who fixes the rest?