73 GW queueing, and no count of the capacity sitting idle
Ofgem’s minded-to position on DCP 412 came out on 16 October. E.ON wants high-capacity, low-use sites moved into a cheaper residual charging band, and Ofgem is minded to say no. The consultation closes on 11 December. Read the full post
Most of the money is on the transmission side, which uses the same bands. For a high voltage site in the top band, the transmission fixed charge would fall from about £523 a day to about £184 (para 7.15).
That matters for the connection queue because the bands are set on capacity holdings where the data exists (para 3.5). Whatever the residual was designed to do, in practice it is part of the cost of holding capacity a site does not draw, and cutting it weakens the reason to give unused capacity back.
Meanwhile Ofgem’s own Curate consultation counts around 73 GW of data centre demand, across roughly 315 projects, waiting to connect. The DCP 412 document does not mention data centres once.
The rules already have a route for this. Under clause 12.11C of the National Terms of Connection, if a metered site never goes above 75% of its Maximum Import Capacity in any 12 consecutive months, the network operator can propose a reduction. Nothing changes unless the customer agrees or Ofgem decides it.
Some network operators publish substation headroom, and some net off contracted demand, but I have not found a published count of how much agreed capacity at existing sites sits below that 75% line, or where it is. Ofgem’s impact assessment describes the number of eligible sites only as small (para 7.8) and had no data for extra high voltage (para 7.11).
The data could probably be gathered by asking site owners directly, or from the half-hourly readings held by the companies that supply the power.
If network operators published agreed capacity against peak draw, substation by substation, how much of that 73 GW do you think could connect sooner?
Analysis. Sources: Ofgem, DCP 412 minded-to consultation (16 October 2026); Ofgem, Curate consultation (July 2026); ENA, National Terms of Connection v19.0.
Earlier posts and articles are archived at markdmoore.co.uk