A free resource: data centre schemes in development across the UK, each qualified from primary sources and rated by how it plans to be powered. Edition 1 was published on 13 October 2026; this is Edition 2, published on 10 November 2026. The local response layer, the first stage of the Village Hall Index, was added on 20 November 2026.
Under constant review, changes or additions will be made to the map as soon as they are processed.
One further layer follows on 27 November: who ultimately controls the schemes. Corrections and missing schemes are welcome at mark@markdmoore.co.uk, with a link to the planning record.
Proposed and under-construction data centre schemes only. This is not a map of all UK data centres: operating sites are not shown.
Data centre schemes in development in the UK: proposed, consented or under construction, including expansions of existing sites. It is not a population of UK data centres; operating data centres are excluded unless an undelivered expansion qualifies, and then only the expansion is shown. Capacity is the undelivered element only; operating capacity is out of scope. Schemes below 5 MW are excluded.
A scheme appears only when four facts are each stated in a primary source (developer, planning authority or government): a named site, a capacity figure, a supply arrangement, and a dated status. Trade press is not used to qualify a scheme. Capacity figures measure different things and are shown as stated.
Schemes in development that do not yet meet all four tests. They are shown so the map's coverage can be judged, not as confirmed schemes. Sizes on the watch list may come from trade press and are labelled by source; a scheme moves onto the map only when every test is met from a primary source. Candidates have every test held or awaiting verification; the others are missing at least one. Readiness colours (hollow circles): Green (G) one item to verify and nothing failed; Amber (A) two or more to verify, or one test failed; Red (R) two or more tests failed; light blue (N) planning not commenced.
Green: new clean supply contracted to the site, or co-located with it, with the counterparty or asset named, and no on-site fossil prime power. Amber: grid supply only, or a clean-power claim not tied to a named new asset. Red: on-site or dedicated gas or other fossil generation planned as primary or bridging power. Standby plant is recorded but does not change the rating. A light-blue ring marks a scheme at pre-application; its fill still shows the supply rating.
This is the light pass only, shown as a ranking. Schemes with a recorded objection count are ranked by that count; where two schemes have the same count, the one with more institutional objections ranks higher, and schemes equal on both share a rank (shown with =). A dagger (†) marks a rank resting on a count that is reported, counted from published comment documents, or a minimum, rather than certified from the council record; it may move when the certified count is read. Institutional objections are formal objections from elected representatives (councillors, MPs, MSPs, MSs, MLAs), objecting community, parish or town councils, and the council's own specialists or statutory consultees. Schemes without an objection count, including those where planning has not commenced, are listed but unranked. The scored Village Hall Index (opposition intensity, combining volume relative to ward population, organised and elected opposition, professional objections and the developer's community benefit and engagement) is in development and is not yet shown. The ranking measures recorded opposition only; it does not measure local support or acceptance. Counts include template and non-resident submissions. Objection, support and neutral counts exclude formal objections from councils and elected representatives, which are counted separately as institutional objections; objections from statutory undertakers and safeguarding bodies protecting their own assets are recorded but not counted.
Public facts on local response to each scheme: representations on the planning record, organised groups, elected positions, published community benefit and engagement. Colours: Green (G) 0 to 50 objections; Amber (A) 51 to 999; Red (R) 1,000 or more; light blue (N) where planning has not commenced; grey (P) where the objection count is pending or not available: the planning record has not yet been read, the consultation is still open, or the consenting route (such as a Local Development Order) produces no published count. Grey does not indicate local acceptance. Where a watch-list scheme has been assessed, its objection figures appear in the watch list table. Each pop-up states the basis of its count: certified (from the council record), published floor or document count (comment documents published by the council, counted by stance), reported (from press, pending the council count) or a stated minimum.
Base map: Natural Earth country boundaries, roads, urban areas and populated places at 1:10m (public domain), held in the page; no map service or API key is used. The road layer shows motorways and principal roads only and is indicative at local scale. Positions are geocoded: postcode centroids from postcodes.io (from the planning record where held, otherwise from a directory listing), published site points, or named-site coordinates; six schemes with no locatable site are placed at the nearest locality. Each pop-up states the basis. Owners are shown by platform; private individuals are not named.